6 Dec 2019

N19 Shannon Access Contract Signing

Overview


plus

Clare County Council in partnership with Transport Infrastructure Ireland (TII) have awarded the planning and design for the N19 Shannon Airport Access Road Scheme.

Image of Clare County Council representatives with Beren DeHora, Director of Infrastructure, at N19 Shannon Access Contract Signing meeting held October 2019.
Photo of Clare County Council representatives with Beren DeHora, Director of Infrastructure (seated far right), at N19 Shannon Access Contract Signing meeting held on 14th October 2019.

The Project shall provide a high quality road improvement scheme on the N19 National Primary Road between Drumgeely Roundabout and Knockbeagh Point Roundabout on approach to Shannon International Airport. The proposed scheme is approximately 2.2 kilometres in length and the existing cross section comprises primarily of single carriageway cross section.

FT and Clandillon Civil Consulting will provide Technical Consultancy Services to Clare County Council, including the Engineering, Environmental, Economic and Appraisal services required to successfully deliver the project through the planning and design phases (TII Project Management Guidelines Phases 1 to 4 inclusive). The Phase 1 to 4 work will be completed within 39 months and is broken down in to the following Phases and associated durations;

  • Phase 1 (Concept and Feasibility), 3 months duration
  • Phase 2 (Options Selection), 9 months duration
  • Phase 3 (Design and Environmental Evaluation), 18 months duration
  • Phase 4 (Statutory Processes), 9 months duration

Click here for FT’s Infrastructure team experience on road projects.

 

 

Please contact info@ftco.ie to progress with this application.